Dumkhar Dam

From Bharatpedia, an open encyclopedia
Information red.svg
Scan the QR code to donate via UPI
Dear reader, We need your support to keep the flame of knowledge burning bright! Our hosting server bill is due on June 1st, and without your help, Bharatpedia faces the risk of shutdown. We've come a long way together in exploring and celebrating our rich heritage. Now, let's unite to ensure Bharatpedia continues to be a beacon of knowledge for generations to come. Every contribution, big or small, makes a difference. Together, let's preserve and share the essence of Bharat.

Thank you for being part of the Bharatpedia family!
Please scan the QR code on the right click here to donate.

0%

   

transparency: ₹0 raised out of ₹100,000 (0 supporter)


Coordinates: 34°28′09″N 76°40′06″E / 34.46917°N 76.66833°E / 34.46917; 76.66833 Dumkhar Dam is a proposed 45 MW run of the river power project on the Indus river in the Leh district of Ladakh, India. The project cost is Rs. 5,274.5 million including interest during construction at June, 2003 price levels.[1]

Technical specifications[edit]

Dam
Type: Concrete gravity dam
Height of dam above: 42 m
Length of dam at top: 220 m

Diversion tunnel
Number: 2
Dia & Shape: 10 m dia horse shoe
Length: 450 m

Reservoir
Full reservoir level (FRL): El 2856 m
Maximum water level (MWL): El 2856.0 m
Min.Draw Down Level (MDDL): El 2853.0 m

Gross storage
at FRL: 26.4 Mcum
at MDDL: 23.0 Mcum
Area under submergence at FRL: 2.85 km2

Spillway
Design flood: 4650 m3/s
Type: Orifice type
Crest elevation El 2830 m
Number & size of spillway opening: 4 No, 8.2 m x 12 m
Energy dissipation: Stilling Basin
Length of spillway: 56.8 m

Intake
Invert level: El 2841 m
Number: 3
Size of gate opening: 3.2 m x 4.0 m
Trash rack: Inclined type

Penstock
Number: 3 Nos
Size: 4 m dia
Shape: Circular
Design discharge: 67.23 m3/s

Power house
Type : Surface
Size
Machine Hall: 50 mX 19.5 m
Service Bay: 23m X 19.5m
Installed capacity: 3X15 MW
Number of units: 3 Nos
Type of turbine: Vertical shaft Kaplan
Maximum gross head: 32m
Rated net head: 27.83 m

References[edit]

  1. "Preliminary Feasibility Report Dumkhar HE Project 3 X 15 MW" (PDF). Ministry of Power. Archived from the original (PDF) on 3 March 2016. Retrieved 15 June 2013.

Template:Hydrography of Jammu and Kashmir Template:Power Plants of Jammu and Kashmir