Hassan–Bangalore section

Hassan-Bengaluru section belongs to Bangalore division of South Western Railway Zone.

Hassan-Bengaluru section
Overview
StatusOperational
OwnerIndian Railways
LocaleKarnataka
TerminiHassan
Chikbanavara near Bengaluru
Service
Operator(s)South Western Railway
History
Opened2017
Technical
Track length166 km (103 mi)
Number of tracks1
Track gauge5 ft 6 in (1,676 mm) broad gauge
Route map
Template:Hassan–Bangalore section

HistoryEdit

The rail line from Hassan to Bangalore via Shravanabelagola, Kunigal, Nelamangala was announced in Railway Budget 1996. Later the work was started in the year 1998.[1] There are two sections in this line. One is from Hassan to Shravanabelagola and the second one is from Shravanabelagola to Nelamangala and Bangalure.[2]

InauguralEdit

A goods trial run was completed by 7 January 2006.[3] The line was opened to traffic by 31 January 2006.[1] Special trains were introduced on this line during Mahamastakabhisheka festival in 2006.[4]

Stations on this LineEdit

ReferencesEdit

  1. 1.0 1.1 "Train service may start ahead of Mastakabhisheka". The Hindu. 27 January 2006. Archived from the original on 7 March 2006.
  2. "Bengaluru–Hassan broad gauge line may open next month". The Times of India. 24 February 2017.
  3. "Trial run on rail line between Hassan and Shravanabelagola". The Hindu. 7 January 2006.
  4. "Special trains to Shravanabelagola from Tuesday". The Hindu. 5 February 2006. Archived from the original on 21 May 2006.