Agra Metro

From Bharatpedia, an open encyclopedia
Information red.svg
Scan the QR code to donate via UPI
Dear reader, We need your support to keep the flame of knowledge burning bright! Our hosting server bill is due on June 1st, and without your help, Bharatpedia faces the risk of shutdown. We've come a long way together in exploring and celebrating our rich heritage. Now, let's unite to ensure Bharatpedia continues to be a beacon of knowledge for generations to come. Every contribution, big or small, makes a difference. Together, let's preserve and share the essence of Bharat.

Thank you for being part of the Bharatpedia family!
Please scan the QR code on the right to donate.

0%

   

transparency: ₹0 raised out of ₹100,000 (0 supporter)



Agra Metro
File:Lucknow Metro Logo.svg
UPMRC logo
Overview
OwnerUttar Pradesh Metro Rail Corporation
Area servedAgra
LocaleAgra, Uttar Pradesh
Transit typeRapid transit
Number of lines2
Number of stations27 (Phase 1)
Operation
Began operationSeptember 2025 (Projected)
CharacterElevated & Underground
Train length3 Coaches
Technical
System length30 km
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Electrification750 V DC third rail
Average speed29.40 km/h (18.27 mph)
Top speed90 km/h (56 mph)
System map

AgraMetroRouteMap1.jpg

Agra Metro is an under-construction rapid transit network in Agra, the third largest city in the Indian state of the Uttar Pradesh. The Detailed Project Report (DPR) was submitted in 2014 and cleared by the Uttar Pradesh government cabinet in 2015. However, due to the formation of a new government and a new Metro Rail Policy, a revised feasibility report was created with the government finally approving the project in early 2019. The Agra Metro is set to consist of two metro lines, with a total length of about 30 kilometres (19 mi).

History[edit]

As of July 2016, DPR has been prepared by RITES and submitted to the state government.[1]

On 28 February 2019, Union Cabinet approved the metro project in Agra worth 8379.62 crore.[2][3]

December 2020: Prime Minister Narendra Modi inaugurated the Civil Construction work for Agra Metro Project.

Project highlights[edit]

The cost of construction is estimated at 350 crore per km. The cost will be evaluated based on the June 2015 price index.

Agra Metro Rail Project will have 2 corridors that will pass through the heart of the city and will connect prominent tourist places including Taj Mahal, Agra Fort, and Sikandra as well as ISBT, Raja Ki Mandi railway station, Medical College, Agra Cantonment railway station, Collectorate, Sanjay Place, and surrounding densely populated residential areas.

Highlights of these corridors include:

  1. The length of Sikandra to Taj East Gate corridor 14.00 km, which is partly elevated and partly underground and comprises 13 stations (6-Elevated and 7-Underground).
  2. The length of Agra Cantt to Kalindi Vihar corridor is 15.40 km comprising 14 stations all elevated.
  3. The estimated cost of the project is 8,379.62 crore and the project will be completed in five years.

About 20 lakh population of the city is expected to be benefit by Agra Metro Rail Project directly and indirectly at the time of commencement of commercial operations.

The proposed corridors will be having Multimodal Integration with Railway Stations & BRTS Stations and will have a feeder network of Bus, Intermediate Public Transport (IPT), and Non-Motorized Transport (NMT). The Project will have non-fare box revenue from rental & advertisement as well as Value Capture Financing (VCF) through the mechanism of Transit-Oriented Development (TOD) and Transfer of Development Rights (TDR).

The Agra Metro is scheduled to start operating from December 2022.[4]

Route network[edit]

In Phase 1, 14 metro stations will be built on the first corridor (Line 1) from Sikandra to Taj East Gate and 15 metro stations will be built on the second corridor (Line 2) from Agra Cantt to Kalindi Vihar.[5]

Line 1 (Sikandra - Taj East Gate)[edit]

Length: 14.25 km

Alignment: Elevated (6.569 km) & Underground (7.681 km)

No. of Stations: 14

Stations:

  • Sikandra
  • Guru ka Taal
  • ISBT Bus Stand
  • Shastri Nagar
  • RBS Degree College
  • Raja ki Mandi
  • St. Johns College (Junction)
  • Sarojini Naidu Medical College
  • Jama Masjid
  • Agra Fort
  • Taj Mahal
  • Fatehabad Road
  • Basai
  • Taj East Gate

Line 2 (Agra Cantt - Kalindi Vihar)[edit]

Length: 15.40 km

Alignment: Elevated

No. of Stations: 15

Stations:

  • Agra Cantt
  • Sadar Bazar
  • Pratap Pura
  • Agra District Collectorate
  • Subhash Park
  • St. Johns College (Junction)
  • Sanjay Place
  • MG Road
  • Nehru Nagar
  • Sultan Ganj
  • Kamla Nagar
  • Rambagh
  • Foundry Nagar
  • Mandi Samati
  • Kalindi Vihar

Rolling stock[edit]

In 2020, Bombardier Transportation won the contract to supply the rolling stock and the signalling system, and the project received conditional clearance from the Supreme Court.[6][7]

Status updates[edit]

  • July 2016: Detailed Project Report submitted to the State Government.[8]
  • September 2017: The central government rejected the DPR of Agra Metro as it didn't conform with the new Metro Rail Policy 2017 introduced that month.[9]
  • January 2018: The UP Government Cabinet decides to build metros in Meerut, Kanpur, and Agra.[10]
  • September 2018: Detailed Project Report (DPR) sent by the UP Government to the Central Government.[11]
  • 7 February 2019: The UP Government has allocated 175 crore to start preliminary work in budget.[12]
  • 28 February 2019: Central Government approved the metro project in Agra.[13]
  • 8 March 2019: Foundation stone laid down by Prime Minister Narendra Modi.[14]
  • August 2019: LMRC has requested relevant authorities to transfer land for Metro construction.[15]
  • January 2020: Construction work yet to start as few permissions from the Supreme Court of India, Taj Trapezium Zone Authority (TTZ), Forest department, Archaeological Survey of India and others other departments are pending. Once permissions are in place, land acquisition will take another 3 months.[16]
  • 15 June 2020: TYPSA - Italferr JV wins General Consultant contract[17]
  • July 2020: Bombardier Transportation won the Agra Metro and Kanpur Metro rolling stock and signalling contract. Agra Metro project gets conditional clearance from the Supreme Court. The project which was stuck due to the court stay will now progress fast.[18][19]
  • October 2020: Contract awarded for construction for three metro stations.[20] Civil engineering work to start in December 2020.[21]
  • December 2020: Prime Minister Narendra Modi inaugurated the construction work at the Agra Metro Project Site on 7 December 2020.[22]
  • April 2021: In Agra metro priority section, a total of 688 piles are to be constructed in the 3 km long portion on Fatehabad Road, in which 344 piles are ready, 10 pillars are built, and digging is continued for 3 metro stations.[23]
  • May 2021: UP Metro has built 400 piles out of a total of 686 in the priority section of the Agra Metro project. With this, 45 pile-caps and 16 pillars are also ready. The work of zero discharge facility at Agra Metro depot is also at a rapid pace. For zero discharge facility, Several underground tanks of different capacities will be built in the Agra Metro Depot complex.[24][better source needed] For zero discharge facility, a joint water treatment plant of 1 lakh liter capacity will be set up at Agra Metro Depot. In this water treatment plant, the gray water coming out from the kitchen, washroom, floor cleaning, will be recycled. For this, a plant with a capacity of 70,000 liters will be installed. Similarly, a 30,000 liters capacity plant will be set up to treat such black water by washing the coach and whatever other chemical-rich water will come out. Both the plants will be built in the same building so that they can be used in a better way.[citation needed]
  • June 2021: Construction of depot line for Agra Metro has begun with the commencement of piling work on the depot line with 13 piles already constructed so far.[25][better source needed] The depot line will connect the mainline with the Metro Depot which is under construction at PAC Ground where metro trains will be stabled and maintained. For the depot line, a total of 500 piles, 39 pile capes, and 34 piers will be constructed.[citation needed]
  • June 2021: The casting of the concourse beam of Taj East Gate, the first metro station of Agra Metro, has also started. The piling work has already been completed with the construction of 69 piles of Taj East Gate Metro Station. Currently, the pillars are being constructed in the side grid of Taj East Gate Metro Station. Soon the construction of the concourse level will also start.[citation needed]
  • June 2021: Along with the construction of the Agra Metro Project Priority Section (Taj East Gate to Jama Masjid), UP Metro has also started the construction of the Depot Line. For this, along with starting the piling, the construction of 13 piles has also been completed. The covered train stabling yard, integrated workshop, and pit wheel length are being constructed in Agra Metro Depot with the new PEB (Pre Engineering Building) technique.[26][better source needed][additional citation(s) needed]
  • July 2021: European Investment Bank (EIB) to fund 480 mn euros for Agra Metro Rail Project.[27]
  • Aug 2021: Unique codes of all metro stations in Agra Metro Rail Project get approved by Indian Railways, as of 7 August.[28]
  • Aug 2021: European Investment Bank (EIB) approves and is ready to fund 480 mn euros for Agra Metro Rail Project, as of 10 August.[29]
  • Aug 2021: Taj East Gate Metro Station takes shape, and it will be the first metro station of Agra Metro to be completed, as of 24 August.[30]
  • Sep 2021: Construction begins of Agra Metro's second metro station, Basai Metro Station.[31]
  • Oct 2021: Tenders invited for electrification contract for Agra Metro.[32]
  • Dec 2021: Work on Agra Metro's third metro station, Fatehabad Metro Station, is expected to be completed by December-end.[33]

See also[edit]

References[edit]

  1. "मेट्रो का सपना कहीं सपना ही न रह जाए" [Metro project remains pending in Agra]. Agra City News. 16 February 2016. Archived from the original on 3 July 2017. Retrieved 9 October 2017.
  2. "Kanpur & Agra metro projects get cabinet nod". Business Standard India. Press Trust of India. 28 February 2019. Retrieved 28 February 2019.
  3. "Centre approves Agra, Kanpur metro rail projects". aninews.in. Retrieved 28 February 2019.
  4. "'Agra metro will start operating by Dec 2022' | Agra News - Times of India". The Times of India. 1 November 2020. Retrieved 24 November 2020.
  5. "Agra Metro – Information, Route Maps, Fares, Tenders & Updates". The Metro Rail Guy. Retrieved 19 December 2020.
  6. "Agra Metro Project: अब आएगी रफ्तार, अगले सप्ताह से शुरू होगा मेट्रो के लिए ये काम". Dainik Jagran (in हिन्दी). 24 July 2020. Retrieved 16 August 2020.
  7. IANS (24 July 2020). "Decks cleared for Agra Metro project, with conditions". www.daijiworld.com. Retrieved 16 August 2020.
  8. "Uttar Pradesh govt gets DPRs for Meerut, Agra". The Indian Express. 1 July 2016. Archived from the original on 6 February 2017. Retrieved 9 October 2017.
  9. "Centre rejects metro rail project report - Times of India". The Times of India. 16 September 2017. Archived from the original on 9 October 2017. Retrieved 9 October 2017.
  10. "UP to Start Metro Services in Agra, Kanpur and Meerut". 18 January 2018.
  11. "UP govt sent DPR to Union govt".
  12. Anurag Gupta (8 February 2019). "कानपुर-आगरा को जल्द मिलेगी मेट्रो की सौगात, 350 करोड़ रुपयों से पकड़ेगी रफ्तार". Dainik Jagaran (in हिन्दी). Retrieved 20 March 2019.
  13. "Adityanath thanks Modi for clearing Agra, Kanpur Metro projects". Outlook. Retrieved 20 March 2019.
  14. "कानपुर से पीएम मोदी ने किया आगरा मेट्रो का शिलान्यास, ताजनगरी में हुआ सीधा प्रसारण". Amar Ujala (in हिन्दी). 8 March 2019. Retrieved 20 March 2019.
  15. "तेजी सेे बढ़ रही आगरा की मेट्रो, स्टेशनों के लिए जमीन हस्तांतरण की तैयारी Agra News". Dainik Jagran (in हिन्दी). 22 August 2019. Retrieved 29 August 2019.
  16. "Work on Agra Metro yet to start; may miss deadline | Agra News - Times of India". The Times of India. 21 January 2020. Retrieved 29 January 2020.
  17. "TYPSA-Italferr JV Wins Kanpur & Agra Metro's General Consultancy". The Metro Rail Guy. 15 June 2020. Retrieved 15 June 2020.
  18. "Agra Metro Project: अब आएगी रफ्तार, अगले सप्ताह से शुरू होगा मेट्रो के लिए ये काम". Dainik Jagran (in हिन्दी). 24 July 2020. Retrieved 16 August 2020.
  19. IANS (24 July 2020). "Decks cleared for Agra Metro project, with conditions". www.daijiworld.com. Retrieved 16 August 2020.
  20. Rai, M. K. (23 October 2020). "Agra Metro Line-1's Construction Works Worth Rs 272 Crores Set for award to Sam India". Metro Rail News. Retrieved 30 October 2020.
  21. "दिसंबर से शुरू होगा आगरा मेट्रो का काम, 273 करोड़ की लागत से बनेंगे तीन प्रमुख स्टेशन". Amar Ujala (in हिन्दी). 21 October 2020. Retrieved 30 October 2020.
  22. "Narendra Modi: PM Narendra Modi inaugurates construction work | Agra News - Times of India". The Times of India. 7 December 2020. Retrieved 7 December 2020.
  23. "UP Metro did half piling work of Agra Metro in record time". 24 April 2021.{{cite web}}: CS1 maint: url-status (link)
  24. "Agra Metro: 400 Piles, 45 Pilecaps & 16 Pillars are Prepared". 12 May 2021.{{cite web}}: CS1 maint: url-status (link)
  25. "UP Metro: Agra Metro Project Progress Updates in June 2021". 6 July 2021.{{cite web}}: CS1 maint: url-status (link)
  26. "UP Metro: Agra Metro Project Progress Updates in June 2021". 6 July 2021.{{cite web}}: CS1 maint: url-status (link)
  27. "EIB to fund Agra metro rail project: UPMRC". Hindustan Times. 29 July 2021. Retrieved 28 September 2021.
  28. "Agra Metro Rail Project: आगरा मेट्रो के सभी स्टेशनों के यूनिक कोड को मिली मंजूरी, अब इन नामों से भी जाने जाएंगे ये स्टेशन". Dainik Jagran (in हिन्दी). Retrieved 28 September 2021.
  29. "EIB agrees to fund 480 million euros for Agra Metro Rail Project". Urban Transport News. Retrieved 28 September 2021.
  30. "Agra Metro Rail Project: जल्द आकार लेने लगेगा आगरा का ये मेट्रो स्टेशन, रखा गया पहला डबल टी गर्डर". Dainik Jagran (in हिन्दी). Retrieved 28 September 2021.
  31. "आगरा मेट्रो के काम ने पकड़ी रफ्तार: ताज पूर्वी के साथ अब बसई स्टेशन पर कार्य शुरू, दस महीने में 102 पिलर का निर्माण". Amar Ujala (in हिन्दी). Retrieved 28 September 2021.
  32. "Tender invited for electrification contract for Agra Metro Rail Project". Urban Transport News. Retrieved 23 October 2021.
  33. "आगरा में मेट्रो: तीसरे स्टेशन का काम दिसंबर अंत में होगा पूरा, निर्माण के दौरान ताजमहल की खूबसूरत तस्वीर आई सामने". Amar Ujala (in हिन्दी). Retrieved 6 December 2021.