Dear reader, We need your support to keep the flame of knowledge burning bright! Our hosting server bill is due on June 1st, and without your help, Bharatpedia faces the risk of shutdown. We've come a long way together in exploring and celebrating our rich heritage. Now, let's unite to ensure Bharatpedia continues to be a beacon of knowledge for generations to come. Every contribution, big or small, makes a difference. Together, let's preserve and share the essence of Bharat.

Thank you for being part of the Bharatpedia family!
Please scan the QR code on the right to donate.

0%

   

transparency: ₹0 raised out of ₹100,000 (0 supporter)


Navi Mumbai Metro Line 1
Overview
StatusUnder construction
OwnerCIDCO
LocaleNavi Mumbai, Maharashtra, India
TerminiBelapur
Khandeshwar
Stations20
Service
TypeRapid Transit
SystemNavi Mumbai Metro
Depot(s)Taloja Metro Depot
Rolling stockChina Railway Rolling Stock Corporation (CRRC) Zhuzhou Locomotive[1]
History
OpenedDec 2021 (Planned for Central Park to Pendhar stations)


Dec 2022 (Planned for Belapur to Kharghar sector 14 stations)[2]
Technical
Line length23.4 km (14.5 mi)
CharacterElevated
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Electrification25 kV, 50 Hz AC Overhead catenary[3]
Operating speed32 km/h[4]
Route map
Navi Mumbai Metro Map.svg

Line 1 of the Navi Mumbai Metro is part of the rapid transit rail system for the city of Navi Mumbai, India. The 23.40 km line consists of 20 metro stations from Belapur to Khandeshwar. It is expected to cost 4,163 crore (US$580 million). On 7th May 2021, State-run town planning authority CIDCO conducted a successful trial run on the approach route to and the test track at Taloja metro depot, and claimed that it was “successful in all respects”.[5]

History[edit]

The following dates represent the dates the section opened to the public, not the private inauguration.

History
Extension date Termini Length Stations
April 2020 Belapur Pendhar 11.10 kilometers (6.90 mi) 11
Pendhar MIDC Taloja 2 kilometers (1.2 mi) 1
MIDC Taloja Khandeshwar 10.30 kilometers (6.40 mi) 8
Total Belapur Khandeshwar 23.40 kilometers (14.54 mi) 20

Background[edit]

The feasibility study for the Navi Mumbai Metro was carried out by the Delhi Metro Rail Corporation (DMRC). CIDCO was authorised as the implementing agency of the Belapur-Pendhar-Kalamboli-Khandeshwar line, under the Indian Tramway Act 1886, by the Government of Maharashtra on 30 September 2010.[6][7] The state government later asked the CIDCO to implement the Navi Mumbai Metro project under the Central Metro Act.[8] The detailed master plan for Line 1 was prepared by the DMRC. The proposed route will link Belapur, Kharghar, Taloje, MIDC, Kalamboli and the Khandeshwar railway station, terminating at the proposed Navi Mumbai International Airport.[9]

Construction[edit]

The metro's foundation stone was laid on 1 May 2011 by Chief Minister Prithviraj Chavan, and general foundation work on the system's first phase commenced in October 2011.[10] Line 1's first girder was placed on 13 December 2012.[11][12]

Line 1 is planned to be developed in 3 phases.[6]

Phase Termini Length Stations Cost
Phase I Belapur-Kharghar-Taloja-Pendhar 11.10 kilometres (6.90 mi) 11 1,985 crore (US$280 million)
Phase II MIDC Taloja-Kalamboli–Khandeshwar (extension to Airport proposed) 10.30 kilometres (6.40 mi) 8 1,509 crore (US$210 million)
Phase III Interlink between Pendhar and MIDC 2 kilometres (1.2 mi) 1 574 crore (US$80 million)
Total 23.40 kilometres (14.54 mi) 20 4,068 crore (US$570 million)

CIDCO awarded the contract for civil works in Phase I to six firms. The contract for technical work was awarded to one firm, at an estimated cost of 1,020 crore (US$140 million).[8] Spanish contractor San José Constructora will design and build five stations, located at Central Park, Pethpada, Sector 34, Panchanand and Pendhar.[13] In the second phase, an 8.15-kilometre (5.06 mi) line will be built from Khandeshwar to Taloje MIDC, with seven stations. The third phase will entail the merging of two rail corridors between Pendhar and MIDC with a 2.2-kilometre (1.4 mi) link, forming a loop from Belapur to Khandeshwar.[14][15] A maintenance depot will be constructed on a 20-acre (81,000 m2) plot at Taloja for the circular line, and a temporary maintenance depot will be constructed on five hectares of land at Khandeshwar.[9]

Line 1 was expected to be completed by 2016 but its most likely to miss deadline, trains may roll out only by July 2017.[16] CIDCO has plans to extend Line 1 up to Kalyan - Ulhasnagar -Murbad.[17]

Funding[edit]

Phase I of Line 1 was executed using CIDCO funds. The total cost of Line 1 is estimated to be 4,068 crore (US$570 million).[6]

Stations[edit]

Stage 1[edit]

Template:Navi Mumbai Metro Line 1

Line 1
# Station Name[18] Inter-station Distance (km) Cumulative Distance (km) Opening Connections
1 CBD Belapur 0.06 0.06 CBD Belapur railway station (Mumbai Suburban Railway)
2 Sector 7 (CBD Belapur) 0.71 0.77 None
3 CIDCO Science Park (Kharghar) 1.27 2.04 None
4 Utsav Chowk (Kharghar) 1.37 3.41 Kharghar railway station (Mumbai Suburban Railway) (through Skywalk)
5 Sector 11 (Kharghar) 0.71 4.12 None
6 Sector 14 (Kharghar) 1 5.12 None
7 Central Park (Kharghar) 1 6.12 None
8 Pethpada (Kharghar) 1.32 7.44 None
9 Sector 34 (Kharghar) 1.23 8.67 None
10 Panchanand 1.48 10.67 Suburban Railway
Orange Line 12 (Mumbai Metro)
11 Pendhar 0.95 11.10 None

Stage 2[edit]

Line 1
# Station Name[19] Inter-station Distance (km) Cumulative Distance (km) Opening Connections
12 Khandeshwar 0.10 0.10 Khandeshwar railway station (Mumbai Suburban Railway)
13 Sector 10 (Kamothe) 0.99 1.09 None
14 Sector 2E (Kalamboli) 1.01 2.10 None
15 Sector 13 (Kalamboli) 0.77 2.87 None
16 Sector 7E (Kalamboli) 1.63 4.50 None
17 Kasadi 1.15 5.65 None
18 MIDC Station 1 1.20 6.85 None
19 MIDC Station 2 1.50 8.35 None

Stage 3[edit]

Stage 3 involves the construction of a 2 km link and one station between Pendhar and MIDC, to join Stage 1 and Stage 2.[3]

Infrastructure[edit]

An international consortium of companies including Ansaldo STS, Tata Projects and CSR Zhuzhou will provide the electrical and mechanical systems for the first phase of Line 1. Ansaldo will conduct systems integration and supply train control systems, telecoms, fare collection systems and equipment storage.[20] The metro's standard gauge network would be electrified at 25 kV AC, with power provided via an overhead catenary.[20]

Rolling stock[edit]

In 2014, the Chinese company CSR Zhuzhou signed a contract with CIDCO to supply rolling stock for the first phase of the metro’s Line 1.[20] The three-car trainsets would be 64.6 metres (212 ft) long and 3.1 metres (10 ft) wide, with a passenger capacity of around 1,100 and a maximum speed of approximately 80 kilometres per hour (50 mph).[21] The trains would feature stainless steel bodies, air-conditioning and LED lighting.[21][20]

References[edit]

  1. News, Urban Transport (12 March 2019). "Navi Mumbai Metro receives two 3-coach metro trains". Urban Transport News. Retrieved 14 March 2019. {{cite web}}: |last1= has generic name (help)
  2. "The Navi Mumbai metro to be operational by Dec 2021: CIDCO". Metro Rail News. 2 March 2021.
  3. 3.0 3.1 CIDCO :: Stage-3 Page
  4. CIDCO :: Technical_Parameters Page
  5. May 8, B. B. Nayak / TNN /; 2021; Ist, 01:36. "Navi Mumbai Metro trial run successful | Mumbai News - Times of India". The Times of India. Retrieved 23 May 2021.{{cite web}}: CS1 maint: numeric names: authors list (link)
  6. 6.0 6.1 6.2 CIDCO :: Introduction Page
  7. "Cidco takes Navi Mumbai metro plan ahead". DNA India. 27 Mar 2012. Retrieved 5 April 2012.
  8. 8.0 8.1 Next metro only by 2016 | Latest News & Updates at Daily News & Analysis
  9. 9.0 9.1 "Neither objections nor any suggestions for metro project | Mumbai, World Snap". Worldsnap.com. 2010. Archived from the original on 14 July 2010. Retrieved 31 August 2010.
  10. "Work on first phase of Navi Mumbai Metro Rail begins". The Economic Times. 28 October 2011. Retrieved 30 October 2011.
  11. "Boost for Navi Mumbai Metro". Times of India. 13 December 2012. Retrieved 21 December 2012.
  12. "CIDCO places first girder". Indian Express. 13 December 2012. Retrieved 21 December 2012.
  13. "Navi Mumbai metro tendering".Railway Gazette. 26 June 2012. Retrieved 15 July 2012.
  14. "Railway projects". Cidco. Retrieved 5 April 2012.
  15. "Work on first phase of Navi Mumbai Metro Rail begins". Times of India. 28 October 2011.
  16. Metro likely to miss deadline again, trains may roll out only by July 2017 - Times of India
  17. "Survey soon to extend Metro rail to Kalyan | Navi Mumbai News - Times of India". The Times of India.
  18. CIDCO :: Stage-1 Page
  19. CIDCO :: Stage-2 Page
  20. 20.0 20.1 20.2 20.3 "Navi Mumbai metro E&M contract awarded". Railway Gazette. 24 July 2014. Retrieved 25 February 2015.
  21. 21.0 21.1 "CIDCO opts for wider metro coaches". Mid-Day. Mid-Day Infomedia Ltd. 26 February 2012. Retrieved 5 April 2012.

Template:Navi Mumbai Metro navbox