Kakatiya Thermal Power Station

From Bharatpedia, an open encyclopedia
Information red.svg
Scan the QR code to donate via UPI
Dear reader, We need your support to keep the flame of knowledge burning bright! Our hosting server bill is due on June 1st, and without your help, Bharatpedia faces the risk of shutdown. We've come a long way together in exploring and celebrating our rich heritage. Now, let's unite to ensure Bharatpedia continues to be a beacon of knowledge for generations to come. Every contribution, big or small, makes a difference. Together, let's preserve and share the essence of Bharat.

Thank you for being part of the Bharatpedia family!
Please scan the QR code on the right click here to donate.

0%

   

transparency: ₹0 raised out of ₹100,000 (0 supporter)


Kakatiya Thermal Power Project at Bhupalpalle
Lua error in Module:Mapframe at line 764: attempt to index field 'wikibase' (a nil value).
Official nameKTPP
LocationGhanpur, Warangal district, Telangana
Coordinates18°23′15″N 79°50′22″E / 18.38750°N 79.83944°E / 18.38750; 79.83944Coordinates: 18°23′15″N 79°50′22″E / 18.38750°N 79.83944°E / 18.38750; 79.83944
StatusOperational
Commission dateUnit 1: February 2009
'Under implementation'
Unit 2: 2013
Operator(s)Telangana Power Generation Corporation Limited (TSGENCO)
Thermal power station
Primary fuelCoal
Power generation
Script error: No such module "Infobox power station".
Nameplate capacity500 MW
'Under implementation'
600 MW

Kakatiya Thermal Power Station is located near Chelpur village of Ghanpur mandal in Warangal district of the Indian state of Telangana. The power plant is one of the coal based power plants of TSGENCO

Plant[edit]

This power plant was developed in 2 stages. The first stage comprised one 500MW unit. The unit was synchronized to grid with oil firing on 31.03.2010 at 06:08 hrs. Coal firing was immediately taken up and the load was raised up to 84 MW and the unit was in service with this load for about 1 hour.[1]

Kakatiya TPP Unit-II 1X600MW, was synchronized to the grid at 03:00 hrs. on 22 October 2015 and loaded to 105 MW.

Capacity[edit]

Stage Unit Number Installed Capacity (MW) Date of Commissioning Status
Stage I 1 500 May, 2010 Running
Stage II 2 600 Jan, 2016 Running

[2]

See also[edit]

References[edit]

  1. "Kakatiya Thermal Power Station" (PDF). Central Electricity Authority. Archived from the original (PDF) on 26 September 2010. Retrieved 26 August 2010.
  2. "BHEL commissions 600 MW Thermal Unit in Telangana | Central Chronicle". www.centralchronicle.com. Archived from the original on 25 April 2018. Retrieved 30 May 2017.