Kanaka line
Overview
Native nameKanaka mārga
StatusUnder-construction
OwnerRail Infrastructure Development Company (Karnataka) Limited K-RIDE
TerminiHeelalige
Rajanakunte
Stations17
Service
TypeCommuter rail
Operator(s)Rail Infrastructure Development Company (Karnataka) Limited K-RIDE
Depot(s)TBD
History
Planned openingMarch 2027; 5 months' time (March 2027)[1]
Technical
Line length47.74 km (29.66 mi)
Number of tracksDouble-track
CharacterElevated and at-grade
Track gauge5 ft 6 in (1,676 mm) broad gauge
ElectrificationTemplate:25 kV 50 Hz overhead catenary
Route map
Template:Kanaka Line, Bengaluru Suburban

The Kanaka line is an under-construction Bengaluru Suburban rail line between Heelalige and Rajanakunte. The 35 km (22 mi) long broad-gauge line was approved in 2019. The construction works for the line which is also referred as 'corridor-4' began in 2024. The line is named after the flower Kanaka (Crossandra infundibuliformis) in Kannada.

History[edit | edit source]

The Heelalige to Rajanakunte line via Yelahanka was the longest among the four proposed corridors by RITES in 2019.[2] It was then approved in the following year along with other corridors.[3] The line was then named after the regional flower's Kannada name Kanaka.[4]

In 2024, minister for railways in Karnataka, V Somanna stated that the Mallige (line 2) along with Kanaka (line 4) were prioritised over the other two.[5] In 2024, the pre-construction works for the line had commenced along with acquisition process of private land for the corridor, and work had already commenced on minor bridges and earth-retaining structures.[6]

For phase wise construction works, the line was divided in two packages C4A and C4B. The corridor 4A ran from Heelalige to Kaggadasapura while 4B from Channasandara to Rajanakunte.[7] The line is planned to be opened by March 2027 along with Mallige.[1]

Construction[edit | edit source]

Construction activities of Kanaka line near Dooravani Nagara in East Bengaluru.
History
Section Opening Terminals Length Stations
C4A March 2027 Heelalige Kaggadasapura 20 km (12 mi) 9
C4B March 2027 Kaggadasapura Rajanakunte 27 km (17 mi) 8

Stations[edit | edit source]

Kanaka Line
# Station Name Opening Connections / Transits / Terminals Station Layout Platform Level Type
English Kannada
1 Heelalige ಹೀಲಲಿಗೆ March 2027[1] TBD Side
2 Bommasandra (Future Station) ಬೊಮ್ಮಸಂದ್ರ
3 Singena Agrahaara ಸಿಂಗೇನ ಅಗ್ರಹಾರ
4 Huskuru ಹುಸ್ಕೂರು
5 Ambedkar Nagara ಅಂಬೇಡ್ಕರ್ ನಗರ
6 Karmelaram ಕರ್ಮೇಲರಂ Add→{{rail-interchange}} Lua error in Module:Adjacent_stations at line 446: Unknown line "Red".
7 Bellanduru Road ಬೆಳ್ಳಂದೂರು ರಸ್ತೆ
8 Marathahalli ಮಾರತಹಳ್ಳಿ
9 Bagmane (Future Station) ಬಾಗ್ಮನೆ
10 Doddanekundi ದೊಡ್ಡನೆಕುಂದಿ Add→{{rail-interchange}} Lua error in Module:Adjacent_stations at line 446: Unknown line "Blue".
11 Kaggadasapura ಕಗ್ಗದಾಸಪುರ
12 Benniganahalli ಬೆನ್ನಿಗಾನಹಳ್ಳಿ Add→{{rail-interchange}} Lua error in Module:Adjacent_stations at line 500: attempt to index local 'data' (a nil value).
<span style="background-color:#Lua error: expandTemplate: template "Bengaluru Suburban Railway color" does not exist.; border:0.1em solid #Lua error: expandTemplate: template "Bengaluru Suburban Railway color" does not exist.;"> Mallige  (Under-construction)
13 Channasandara ಚನ್ನಸಂದರ
14 Horamavu ಹೊರಮಾವು
15 Hennuru ಹೆಣ್ಣೂರು
16 Thanisandara ಥಣಿಸಂದ್ರ
17 R.K.Hegde Nagara ಹೆಗಡೆ ನಗರ
18 Jakkuru ಜಕ್ಕೂರು
New station ಹೊಸ ನಿಲ್ದಾಣ
19 Yelahanka ಯಲಹಂಕ <span style="background-color:#Lua error: expandTemplate: template "Bengaluru Suburban Railway color" does not exist.; border:0.1em solid #Lua error: expandTemplate: template "Bengaluru Suburban Railway color" does not exist.;"> Sampige  (Planned)
New station ಹೊಸ ನಿಲ್ದಾಣ
18 Muddanahalli ಮುದ್ದನಹಳ್ಳಿ
New station ಹೊಸ ನಿಲ್ದಾಣ
19 Rajanakunte ರಾಜನಕುಂಟೆ

See also[edit | edit source]

References[edit | edit source]

  1. ↑ 1.0 1.1 1.2 "Railways to construct new terminal at Devanahalli; Bengaluru suburban rail corridor deadline pushed to 2027". The Indian Express. 17 January 2025. Retrieved 17 January 2025.
  2. ↑ "Bengaluru's suburban rail dream now closer to reality". The Times of India. 5 November 2019. ISSN 0971-8257. Retrieved 18 January 2025.
  3. ↑ "Centre approves Bengaluru suburban rail project". Deccan Herald. Retrieved 16 January 2025.
  4. ↑ Philip, Christin Mathew (6 March 2021). "Bengaluru suburban rail corridors likely to be named after flowers". The Times of India. Retrieved 10 July 2021.
  5. ↑ "Bengaluru Suburban Railway Project: 'Corridors 2 and 4 are priority now,' says minister V Somanna amid talks on axing Corridor 3". The Indian Express. 28 November 2024. Retrieved 15 January 2025.
  6. ↑ Vivan, Sridhar. "Bengaluru Suburban Rail corridor 4 construction update". Bangalore Mirror. Retrieved 18 January 2025.
  7. ↑ "Two Firms Bid For Bengaluru Suburban Rail's Packages C4A & C4B - Metro Rail News". 10 September 2024. Retrieved 18 January 2025.