Khurja Super Thermal Power Plant: Difference between revisions

>BrownHairedGirl
 
Line 44: Line 44:
! Stage !! Unit Number !! Installed Capacity ([[Watt#Megawatt|MW]]) !! Date of Commissioning !! Status
! Stage !! Unit Number !! Installed Capacity ([[Watt#Megawatt|MW]]) !! Date of Commissioning !! Status
|-
|-
| Stage I || Unit I || 660MW  || Nov 2022 ||Tenders floated
| Stage I || Unit I || 660MW  || Feb 2024 ||Tenders floated
|-
|-
| Stage I || Unit II || 660MW  || April 2023 ||Tender floated
| Stage I || Unit II || 660MW  || Dec 2024 ||Tender floated
|-
|-
|}
|}